Project Title: Sunriver Trail Kiosk Project

Project Title: Sunriver Trail Kiosk Project

Project Solicitation Number (if any):

Project Description: This RFP is for the construction of the three two-panel kiosks, The kiosks will be constructed out of wood posts, columns and plywood boards, and follow a similar design as the kiosk located at the Phil’s Trails parking area near Bend, Oregon. COTA is providing drawings of a three-panel kiosk that will be the basis for the construction of the two-panel kiosks for the Sunriver Trails. The contractor will utilize the three-panel drawings for the design and construction of the two-panel kiosks.

Company/Organization/Agency Submitting Contract: Central Oregon Trail Alliance

Primary Contact for Contract Information: Bruce Schroeder

Email Address: bruce.schroeder@cotamtb.com

Closest City to Project: Bend

State/Province/Region: OR

Anticipated Project Start Date: 6/29/2020

Application Deadline: 6/19/2020

Additional Project Bid Information: Bids are due by June 19, 2020. Notice to Proceed will be made by June 29, 2020 with work starting within 10 days of this Notice. The project will be completed by August 13, 2020. (Please note that this timeline may need to be adjusted to address COVID-19 health restrictions.)

Full copy of the project RFP

Attachment A - Location Map

Attachment B - Design

Previous