COTA - Wanoga Infield Skills Area - OR
Project Description: Central Oregon Trail Alliance (COTA), in collaboration with the Deschutes National Forest (DNF) Bend-Fort Rock Ranger District, is seeking bid proposals from qualified Design-Build Trail Contractors (Contractor) to provide professional services to re-construct a skills area in the DNF at the Wanoga Sno-park.
This RFP is for the re-construction of the Wanoga in-field pump track in the DNF near Bend, Oregon. The pump track has deteriorated and is hard to maintain. The goal is to rebuild the pump track as a skills area with 3 to 4 distinct lines: Progressive jump lines and Drop zone with progressive sized drops. An easy return climbing route will also be included.
The schedule is as follows:
● RFP released: January 10, 2023
● Proposals due: February 7, 2023
● Award: February 15, 2023
● Design completed and approved: April 15, 2023
● Trail work: May - July (exact timing will be weather and fire restriction dependent)
● All work complete: July 31, 2023
To Apply:
● Find the full Request For Proposal PDF and more information on our website: https://www.cotamtb.com/request-for-proposals.html
● The work will be awarded based on best value. The maximum budget is $15,000.
● All proposals must be received by 5 p.m. Pacific time Tuesday, February 7, 2023.
● Please submit your proposal electronically to alex.brieger@cotamtb.com.
Company/Organization/Agency Submitting Contract: Central Oregon Trail Alliance
Primary Contact for Contract Information: Alex Brieger
Email Address: alex.brieger@cotamtb.com
Closest City to Project: Bend
State/Province/Region: Oregon
Country: United States
Pre-Bid Meeting Date:
Pre-Bid Meeting Time:
Anticipated Project Start Date: 4/1/2023
Application Deadline: 2/7/2023
Additional Project Bid Information:
Date Submitted to PTBA: 1/11/2023